By Josh O’Gorman
Staff Writer | October 09,2013
Rutland Herald
KILLINGTON — Some parties involved in the
proposed Killington Village are celebrating that the project received
permits, but a town official is questioning a permit requirement for a
wide-ranging traffic study.
Killington-based developer SP Land
Company received two Act 250 permits Monday from the District 1
Environmental Commission to build 193 residential units, a 32-unit
subdivision, 31,622 square feet of commercial and retail space, and a
77,000-square-foot skier services building to replace the Ramshead and
Snowshed base lodges.
The permits will also allow for
construction of a 1,276-car parking lot and realignment of Killington
Road and the parking lot of the Killington Grand Resort Hotel.
SP
Land President Steven Selbo said Monday he was excited to receive the
permit and was “cautiously optimistic” about the project going forward.
“I
called Steve Selbo to congratulate him on getting the permit,” Select
Board Chairman Chris Bianchi said Tuesday. “The Select Board has been
unanimous in supporting the village project. I will continue to support
SP Land on the board as a select person, and I hope the board will
continue to support the village, because we need it.”
The Select
Board expressed its support for the project in letters to the Rutland
Regional Planning Commission, one of the parties in the permit process.
Kris Hughes, executive director of the RRPC, also celebrated the
issuance of the permit.
“We’re delighted the permit has been
issued and it’s moving forward,” Hughes said. “I think good planning is a
good idea but I wouldn’t want it to get in the way of the project. We
need economic development in this area and it’s important this project
goes forward.”
The RRPC made suggestions to the commission. One
recommended that, upon completion of the first phase, SP Land conduct a
corridor study looking at the traffic impact on Killington Road, and as
well as on Route 4 and Route 103 as far as I-89 and I-91, respectively.
The
other planning groups with party status — the Southern Windsor County
Regional Planning Commission and the Two Rivers-Ottauquechee Regional
Commission — suggested to the District 1 Environmental Commission that
the corridor study be required. In fact, the corridor study was made a
condition of the permit.
Tom Kennedy, executive director of the
SWRPC, said the corridor study — which was opposed by SP Land throughout
the Act 250 process — has been part of permits for similar projects in
the past.
“We have a precedent for this,” he said “We started
this back in the 1990s with the expansion of Killington and Okemo. It’s a
process where the parties need to sit down and see what needs to be
done.”
Kennedy added. “I’m a skier and I ski at Killington and I
think everyone wants to see Killington succeed in what they’re trying to
do.”
David Rosenblum, chairman of the Killington Planning
Commission, expressed satisfaction that the permit was issued, but was
less than thrilled by the corridor study requirement.
“I’m very
happy to see it was issued, and for the most part it seems workable,”
Rosenblum said. “I still don’t think a developer should be burdened with
a traffic study.”
Calling a traffic study the “domain” of the
state Agency of Transportation, he also suggested the study covers a
larger geographical area than is needed.
“How much traffic SP
Land’s project creates from Killington Road down to Route 4 seems
appropriate, but the scope of this study seems too broad,” he said.
Rosenblum also noted that it took 20 months for the permit to be issued.
“I’m embarrassed it took so long and people should probably look at why it took as long as it did,” he said.
josh.ogorman