Mountain Times
December 5, 2018
Plans await cost estimates in advance of a Town Meeting Day vote
By Polly Mikula
The
town of Killington has preliminary designs for a new public safety
building. Plans call for a multipurpose 15,260-square-foot building to
house the volunteer fire department, search and rescue, and town police
department. The plans have six bays for firetrucks in the front of the
building and two in the rear for light rescue and police, a hose tower, a
DUI holding cell, lockers, offices and a public meeting room.
The
building will be located off Killington Road on a four-acre lot just
southeast of Woods Road, across from Peppino’s and the Mountain Sports
Inn. Voters approved the
land purchase for a public safety building last year and the town has
been working on designs for that site, since. The plans are expected to
come in under $4 million. Town Manager Chet Hagenbarth said he expects
to have a solid number for citizens to vote on at Town Meeting Day,
March 5, 2019.
If voters
approve the bond to build a public safety building, construction would
likely be in the summer 2020, due to scheduling the new bond payments to
begin after other current debts are set to retire, Hagenbarth said.
“The goal is to keep the debt service flat,” he explained.
The
designs for the public safety building have been led by the Fire
Department Facility Review Committee, a group of citizen volunteers who
were originally tasked with weighing options for the town when the
current fire department building was found to be in violation of state
code in 2013.
Citizens on the committee include: Steve Finneron (chair), Otto Iannantuoni, Vito Rasenas, Andrew Salamon and Richard Kropp.
After
deciding that fixing the current fire house was not in the town’s best
interest (due to high costs and compromises), the committee began
searching for alternatives – beginning with a new site.
After
vetting 13 properties, the committee put the 4-acre site to a public
vote. The 30-year, $634,000 bond to secure that land passed 102 to 84 on
Sept. 5, 2017.
Included in
that bond was the purchase of the 4-acre parcel for $525,000; civil
engineering designs for $21,500; and fees for schematic architectural
design and construction estimate for $87,500.
Since then, the committee has been working on a future building design.
“It’s
been a tedious process, but very educational,” said Finneron, who is
the chair of the Fire Department Facility Review Committee and the chair
of the Select Board. “Who knew that you had to have a specific drain in
the holding cell so that folks couldn’t flush narcotics, for example …
or that the slope of the floor in a fire station ought to be a specific
angle so that the floor stays dry … there are so many particulars that
make big differences,” he said.
The
Fire Department Facility Review Committee frequently consults with the
Killington Fire Department, Killington Police and Killington Search and
Rescue to ensure that the design specifics meet their needs, Finneron
said. It also has hired DEW Company as the construction manager to
oversee the bidding process and (eventually) the buildout of each part
of the construction process, should voters approve the building plans on
Town Meeting Day. Additionally, the committee hired Northeast
Collaborative Architects (NCA) as the design firm, which has worked on
many similar municipal buildings and has given the committee multiple
options to solve identified needs.
The public safety building does not trigger an Act 250 hearing as the project is under 10 acres, Finneron noted.
The
site and the preliminary design will allow the town to expand the
building for future uses, as they arise in the future, Hagenbarth said.
“The design is intentionally expandable, unlike pre-engineered buildings
which do not allow for future changes,” he said. “We must evaluate
costs for the best value over time. If we focus too much on saving
pennies now, it will cost us dollars later.”
“This
building will be part of the town for 50-60 years,” added Finneron. “We
need it to be able to grow and change with the town’s needs … We need to consider the cost of maintenance over time,” he said.
Finneron
and Hagenbarth both said they hope all public safety services could be
consolidated in the new public safety building, including an underground
cistern for the fire station. However, “all options are on the table”
Finneron said.
The current
fire station could continue to serve some functions, particularly if
obstacles are found that limit possibilities, such as a cistern, at the
new site.
“The preliminary
plans are now mostly finished,” said Finneron. “Now we’re just tweaking a
few details and working on the right materials to use.”
“We’re
also at a stage where we’d love more community input,” he said. “What
can you bring to the table? Do you have ideas or solutions we’re not
thinking about? If so, come to our meetings!” Finneron said.
The
Fire Department Facility Review Committee will be presenting the
preliminary design to the Planning Commission to ensure compliance with
local zoning regulations on Dec. 12. Visit killingtontown.com for the
date and location of the next review committee meeting .
No comments:
Post a Comment