Resort unveils new/upgraded lifts, improved terrain, and more summer attractions
By Polly Lynn Mikula
KILLINGTON—On
Thursday, March 1, approximately 400 people gathered in the Oscar Wilde
Ballroom at Killington Grand Resort for a “Resort Update” presented by
Mike Solimano, president and GM of Killington and Pico.
The turnout was impressive, with many local business people saying it was the largest crowd they’d ever seen at a resort update.
Even
Solimano was surprised as folks continued to flood in well after all
the seats were filled. “We didn’t anticipate this many,” he said, just
before beginning his presentation at 5 p.m. “It’s great to see so many
people come out for this,” he added.
Solimano begun his
presentation outlining planned investments of over $16 million at
Killington and Pico ahead of the 2018-19 season.
Some
of the biggest winter enhancements will include: a new 6-person high
speed bubble chairlift at Snowdon ($7.8 million), new lift service at
South Ridge, upgrades to the K-1 Express Gondola including new cabins
($2.2 million), hands-free lift access gates at both Killington and Pico
($1.5 million) as well as improved intermediate trails and new ski
bridges and tunnels at key intersections.
“While we are
committed to staying core to our beastly advanced terrain, we are also
putting the focus on our blue family-friendly terrain,” said Solimano.
“The investments we’re making will re-shape the guest experience for
years to come. Uphill capacity will increase to 48,000 per hour and the
downhill enhancements will create more diverse terrain for all levels of
skiers and riders.”
Solimano also presented new
investment plans for this summer, including a Ninja-style obstacle
course (called WreckTangle), exercise pod and jogging path, and a
chocked-full event schedule including the addition of the Mountain Bike
US Open Aug. 1-5.
Summer investments this year will
total just $500,000, but investments over the past five years come to $6
million, Solimano explained. (The resort invested $500,000 in 2014, $3
million in 2015, $1 million in 2016, $1 million in 2017 and $500,000 in
2018.)
Mountain Biking has seen the lion’s share of
investment dollars and the resort has seen that investment pay off in
correlated rider visits. In 2013, before the five-year buildout of
mountain biking, the resort reported just 2,000 rider visits, in 2014 it
grew to 4,900, then 8,060 in 2015, then 12,000 in 2016 and hit a
whopping 23,000 last summer; representing a total growth of 91 percent,
said Solimano showing a chart outlining this growth.
Solimano
said he hopes, one day, the resort will be able to operate the lifts
year-round “with no break between skiing and riding.”
New Snowdon six-person bubble chairlift
A
new six-person high-speed, bubble chairlift will be installed ahead of
the 2018-19 ski season. The new Snowdon chair, manufactured by
Leitner-Poma, features a bubble shield that will protect skiers and
riders from wind and weather as they ascend 1,100 vertical feet to the
Snowdon Mountain peak, which features primarily intermediate cruising
terrain. There also will be a storage facility built to house chairs in
inclement weather to assist when weather impedes operations.
The ride, “which used to take 10 minutes (and feel like 15)” as Solimano said, will now take just 4.5 minutes to the top.
South Ridge Quad
The
highly anticipated return of lift service in the South Ridge area will
occur with the relocation of the refurbished, Snowdon Quad chairlift.
The South Ridge Quad will load and unload in the same locations as the
old South Ridge Triple and will have a length of 3,900 feet and a
vertical rise of approximately 875 feet. The South Ridge Quad will
provide easier access to trails such as Pipe Dream and an additional way
to connect back to the north side of the resort from Bear Mountain.
K-1 Express Gondola
In
addition to numerous upgrades to the K-1 Gondola in the past few years.
Killington will replace all cabins with brand-new Leitner-Poma Sigma
eight-person cabins which will be stored in a new cabin storage facility
to improve reliability and de-icing time. The haul rope will also be
replaced and improvements to the loading area are also planned. All
ahead of next season.
The K-1 Gondola will continue to
run on electricity generated by BioGas, through a program commonly known
as Cow Power as part of our commitment to POWDR’s Play Forever using
renewable energy.
New RFID gates
Killington
Resort and Pico Mountain will introduce Axess smart gates with RFID
(radio-frequency-identification) at lift access points. This technology
will improve the guest experience by the use of hands-free automated
gates instead of manual barcode scanning.
Terrain improvements
Killington
Resort will continue to improve the on-mountain experience for its
intermediate skiers and riders with a number of terrain improvements on
the mountain. These improvements include trail widening and adding
tunnels and bridges at the following intersections:
- Great Northern and Bunny Buster and Mouse Trap
- Great Northern and Upper Chute
- Great Northern and Lower Chute
- Snowshed Crossover at the Stash and Skyeburst
Tunnels,
bridges, regrading will improve the experience on several key
intermediate trails by limiting trail intersections in high traffic
locations and removing pinch points for more top to bottom trail runs.
Snowdon Poma relocation
The
Snowdon Poma lift will move to Swirl to create a dedicated race
training venue for Killington Mountain School and Killington Ski Club.
This move will open additional terrain to guests in the Snowdon area and
allow for uninterrupted top to bottom skiing and riding.
Summer improvements
Summer
operations continue to expand at Killington Resort with a new Woodward
WreckTangle and additional summer attractions to be added to the
Adventure Center.
The WreckTangle is an outdoor ninja
obstacle challenge featuring nine different sections of unique and
fun-filled obstacles to conquer including cargo nets, balance beams and
rope swings. Additionally, Killington’s Mountain Bike Park will make
improvements to beginner terrain, unveil the newly completed Krusty
Trail on Ramshead and extended riding hours.